Egypt and Morocco have the region's largest planned low-carbon hydrogen pipelines for 2030, but GlobalData says delivery is uncertain: most capacity remains at feasibility stage and exports face weak offtake and a Western Sahara legal complication.

Morocco's export plans carry a legal complication: on 4 October 2024, the Court of Justice of the European Union (CJEU) annulled two EU-Morocco Council decisions concerning agricultural trade and fisheries agreements applied to Western Sahara. The court held that Western Sahara is "separate and distinct" from Morocco under international law and that the territory's people must be regarded as a people. Extending an agreement to Western Sahara requires their consent, the CJEU judgment said. The rulings concerned trade arrangements, not hydrogen specifically, but their reasoning is relevant to proposed hydrogen and ammonia exports, including infrastructure located in the territory.

GlobalData puts Egypt's planned low-carbon hydrogen capacity at about 5.1 million tonnes a year by 2030, ahead of Morocco's 4.5mtpa. These are pipeline targets, not operating production. About 90% of Egypt's expected capacity and half of Morocco's remain at feasibility stage.

Export ambitions meet delivery and legal risks

The pipeline is the largest in the Middle East and Africa, which GlobalData ranks second to Europe among regional markets. Egypt's ACME Group is targeting 2.1mtpa of green hydrogen at Ain Sokhna. In Morocco, Mohring Energie's NexTerra project aims for 1.4mtpa. Projects at these scales need renewable generation and electrolysers, plus water supply and export infrastructure. They also need finance and buyers.

Both governments are counting on exports to Europe, where demand for renewable hydrogen derivatives is growing. Morocco has selected five investor groups to negotiate six projects valued at about $32 billion, with some proposed sites in Western Sahara. A related hydrogen report also covered uncertainty over a developer's planned locations in the territory. The CJEU's decisions did not rule on hydrogen projects, but the court's findings raise a distinct legal question for EU-linked arrangements involving Western Sahara. GlobalData analyst Clarice Brambilla said the ruling could complicate Morocco's export plans.

The court temporarily maintained the effects of the annulled decisions for a limited period while the EU considered the consequences. The CJEU's judgment does not itself invalidate Morocco's hydrogen projects.

Announced capacity outpaces committed demand

GlobalData's database lists 75mtpa of potential low-carbon hydrogen capacity worldwide by 2030. About 4mtpa is under construction or being commissioned, while only around 10% of planned capacity has an identified offtaker; fewer projects have binding contracts. The figures describe announced project capacity rather than a forecast of delivered supply.

Cost and infrastructure are further obstacles. Green hydrogen requires renewable-power assets and electrolysers, along with water-treatment systems; shipping may also require conversion into ammonia or another carrier. GlobalData says close to 60% of planned green capacity for 2030 is still at feasibility stage, compared with a quarter of planned blue capacity.

"Announced capacity is also becoming a less reliable indicator of future deployment, as the sector's focus shifts towards obtaining financing, reaching final investment decisions and securing long-term demand," said Brambilla, energy transition analyst at GlobalData.

Regional forecasts point to a green shift

Global low-carbon hydrogen production stood at 2.3mtpa at the end of 2025, and GlobalData forecasts it will more than double to 5.7mtpa by the end of 2026. Developers have announced 65mtpa of green capacity for 2030, against 11.8mtpa of blue; electrolysis is expected to provide 85% of production by then.

Europe's revised Renewable Energy Directive requires renewable fuels of non-biological origin to account for at least 42% of hydrogen used in industry by 2030, rising to 60% by 2035. The requirements are set out in the revised EU directive. In May 2026, the European Hydrogen Bank awarded more than €1 billion across nine projects, representing about 1.1GW of electrolyser capacity. GlobalData forecasts European capacity of 22.95mtpa by 2030, 82% green.

Morocco's first green-hydrogen production is not expected before 2031 even under an optimistic scenario, Badr Ikken, president of Gi3 and former director of IRESEN, told TelQuel. The Chbika project was officially announced during French President Emmanuel Macron's visit to Morocco in late October 2024. TelQuel also reported in 2026 that Morocco's announced projects targeting 2030 had been scaled back to about 27 million tonnes, while projects with a final investment decision or a high likelihood of operating by 2030 represented just over 6 million tonnes.

GlobalData expects blue hydrogen to retain a role in markets with natural gas resources and access to CO₂ storage. Brambilla said securing long-term offtake and coordinating infrastructure are likely to matter more than renewable resources in determining which markets meet their 2030 ambitions.