Morocco Starts Building 3 MW Solar Plant in Jerada

Bruce Maddy Editor Maghreb Insider

Post by Bruce Maddy

Morocco Starts Building 3 MW Solar Plant in Jerada Maghreb Insider © maghrebinsider.com
Morocco Starts Building 3 MW Solar Plant in Jerada © maghrebinsider.com

Work began in Lamrija on a 3 MW first phase backed by 30 million dirhams. The facility is expected to start operating in the second half of 2027 as part of a wider 10 MW agreement.

Once completed, the Lamrija solar facility is expected to generate about 6 gigawatt-hours of electricity a year, equivalent to the annual consumption of more than 4,000 households in Jerada province. The first 3 MW phase is part of a broader development planned to reach 10 MW.

Construction began on November 19, 2026, in Lamrija commune, Jerada province, in Morocco's Oriental region. The Moroccan Agency for Sustainable Energy (Masen) is carrying out the project through its subsidiary, Masen Services, over a seven-month construction period. A Masen representative said commissioning is scheduled for the second half of 2027. The site is part of the Noor Atlas Aïn Béni Mathar complex.

The project follows a framework agreement involving the Ministry of the Interior, the Ministry of Energy, Mines and Sustainable Development, Masen, the Wilaya of Oriental, Jerada province and the Jerada provincial council. The agreement provides for a total planned capacity of 10 MW and an estimated investment of 114.5 million dirhams. That covers the generation facilities, grid-connection equipment and access roads, as MAP reported.

Funding for the first phase

The 3 MW phase has a 30 million-dirham budget. The General Directorate of Territorial Collectivities is contributing 26 million dirhams, while Masen is providing 4 million. Yabiladi reported the funding breakdown. These figures cover the first phase, not the full 10 MW development.

The project sits within a broader 10 MW agreement, with estimated investment of 114.5 million dirhams, including grid connection and site access infrastructure. The energy investment differs in purpose from Libya's planned factory-support drive, covered in Maghreb Insider's earlier report.

Power sales and grid connection

Electricity will be sold over 25 years to the Société régionale multiservices de l'Oriental, also referred to as the Regional Multi-Service Company of the Oriental region. The company will supply the intended users and oversee the plant's connection to the medium-voltage power grid.