Technical talks in Niamey will define the Niger section of a planned Nigeria-Algeria gas corridor designed to carry up to 30 bcm a year. Construction in Niger is scheduled to begin in early 2027.
Designed to carry up to 30 billion cubic metres (bcm) of gas a year, the planned 4,128-kilometre Trans-Saharan Gas Pipeline (TSGP) would carry Nigerian gas through Niger to Algeria, linking it to the country's transmission and export infrastructure and onward routes toward Europe. Niger and Algeria opened talks in Niamey on November 17 to advance technical studies for the Nigerien section and assess a route modified by Niger.
Niger's Ministry of Petroleum Secretary-General Abdoulkarim Mohamed Ali met the Algerian delegation on November 17. The team, which includes representatives of Algeria's Ministry of Hydrocarbons, Sonatrach's Pipeline Transport Division and the National Pipeline Construction Company (ENAC), is scheduled to work in Niger from November 17 to 20. Sonatrach's official account says the agenda includes accelerating route studies, collecting project-stage data, confirming Niger's modified route and assessing its impact.
Route and preparations in Niger
According to Niger's ANP news agency, the discussions cover the precise route and work required before construction can begin. The parties are also defining technical and regulatory studies and considering how Nigerien companies could participate. ENAC is examining procedures to establish a branch in Niger. The Algerian delegation also met Niger's prime minister on November 18.
Africa Monitoring reports that the Nigerien Project Management Unit, the Inter-ministerial TSGP Committee and Niger's national petroleum company, SONIDEP, are involved in the preparatory process. The proposed route is associated with the Trans-Saharan Road corridor; on entering Algeria, it is planned to run from the Niger border toward Hassi R'Mel, the country's principal gas-dispatch hub, connecting with its existing transmission and export systems.
Oil Minister Hamadou Tini said in June that construction of Niger's section is scheduled to start in early 2027. The November meetings remain focused on preparation, including route assessment, technical and regulatory studies, and defining the work required for implementation.
Construction and project timeline
Algeria began work on its section in Adrar province on June 4, 2026. The planned line is to link the Niger border with the Hassi R'Mel gas hub, connecting it to Algeria's existing export infrastructure.
In March, African Petroleum Producers' Organization Secretary-General Farid Ghezali told AL24 News the pipeline could be fully operational by early 2029. The project partners have not announced an official start date. Reuters reported that Nigeria's state-owned NNPC expects discussions on a final investment decision for the full project to begin in 2027. In November, L'Express Algérie reported that the three partners had reached an agreement in principle on the financing structure and put the estimated overall cost at $10 billion to $13 billion. Maghreb Insider has also covered NNPC's investor outreach for a separate Morocco gas route in an earlier report on the project.