TAQA Morocco Secures $133 Million for Boujmil Wind Farm

Bruce Maddy Editor Maghreb Insider

Post by Bruce Maddy

TAQA Morocco Secures $133 Million for Boujmil Wind Farm Maghreb Insider © maghrebinsider.com
TAQA Morocco Secures $133 Million for Boujmil Wind Farm © maghrebinsider.com

Four Moroccan banks are providing $133 million for Boujmil's first phase in northern Morocco. The wind farm is expected to begin generating power in the second half of 2027, initially delivering 96 MW.

Boujmil's first stage is designed to deliver 96 megawatts. At full development, capacity is planned to reach 144 MW, adding 48 MW beyond the initial phase.

TAQA Morocco announced financial close for the first phase on 3 November 2026. Banque Centrale Populaire and Attijariwafa bank are participating in the financing, alongside Bank of Africa and Saham Bank. The phase represents an investment of approximately MAD 1.3 billion. The company has described the transaction as its first green financing. TelQuel reported the financial close and the four-bank consortium. Malik Séna of OnlyBenki noted that MAD 1.3 billion refers to the announced investment, not a disclosed loan amount. The banks did not announce individual allocations or pricing; maturities also remain undisclosed.

Capacity and expected output

Construction began in the fourth quarter of 2025. TAQA Morocco has targeted the first electricity supply for the second half of 2027. At full development, the wind farm is projected to generate electricity equivalent to the consumption of about 120,000 households and avoid approximately 250,000 tonnes of CO₂ emissions annually. The company also expects the project to create direct and indirect jobs. These household and emissions estimates refer to the project at its planned eventual capacity of up to 144 MW.

TAQA Morocco Wind Corporation has been identified as the project company responsible for building and running the project, including its upkeep. The company's announcement described the transaction as its first green financing, backed by four Moroccan commercial banks.

A new part of TAQA Morocco's portfolio

TAQA Morocco says Boujmil advances its strategy to diversify its energy portfolio and build renewable-energy infrastructure. Maghreb Insider's Dakhla projects report examined resource extraction and transport links in Western Sahara, a separate development context from Boujmil's wind-power project.

Founded in 1997, TAQA Morocco has become a major electricity producer through its coal-fired Jorf Lasfar power plant. Its six units have a combined capacity of 2,056 MW.