The 341-kilometre package covers the El-Menea-In Salah-Tamanrasset corridor. MEED's accessible report gives no contract value or bid deadline, so the package must be assessed separately from Algeria's earlier rail awards.
In March 2026, Algeria tendered two railway contracts covering 495 kilometres, with a combined estimated value exceeding $2.5 billion. That figure does not apply to the new package. The 495 kilometres comprise a 265-kilometre Laghouat-Ghardaia section and a 230-kilometre Ghardaia-El-Menea section.
MEED reports that ANESRIF's tender covers a 310-kilometre railway section between Hotel and Moulay Lahcen, part of the planned El-Menea-In Salah-Tamanrasset corridor. The tender notice was issued on 12 October 2026, and bids are due by 10 November. Both individual contractors and consortia may participate. The contract value has not been disclosed.
Separate packages define the investment picture
The earlier contracts covered the Laghouat-Ghardaia and Ghardaia-El-Menea sections. Planned works include stations and viaducts, along with a tunnel and other railway structures. A separate rail contract report covered the Ghardaia-El-Meniaa line.
Keeping the packages distinct matters for contractors weighing the new opportunity. ANESRIF's tender sets experience requirements for single-firm bidders. They must have completed at least 200 kilometres of new railway construction or track-doubling works since 2010. Bidders must also show experience on sections of at least 100 kilometres and railway bridges totalling 800 metres, with individual spans exceeding 30 metres. They must have at least two tamping machines and two ballast stabilisers. The project manager must hold an engineering degree and have at least five years' railway-construction management experience.
Financial qualification requires average annual construction turnover of at least 260 billion Algerian dinars, about $1.96 billion, over the 2023-2025 financial years. Consortium members may combine turnover, but the lead member must meet a threshold of about $1.3 billion. Bids require a bank guarantee exceeding 1% of the offer value when that value is above $7.4 million. They remain valid for 90 days beyond the submission date.
Southern links remain a government priority
On 18 October 2026, President Abdelmadjid Tebboune chaired a Council of Ministers meeting and ordered the immediate launch of the Laghouat-El-Menea-In Salah-Tamanrasset railway project, starting from Tamanrasset. The Algeria Press Service reported the directive as part of the government's wider railway programme. The route links Laghouat, Ghardaia and El-Menea with In Salah and Tamanrasset.
The southern tender is one package within that wider programme. Government discussions have also covered the El-Menea-PK 216 section and a 213-kilometre Tamanrasset-Moulay Lahcen section. The northern Laghouat-Ghardaia and Ghardaia-El-Menea packages are separate from the Hotel-Moulay Lahcen tender.
Algeria's Ministry of Public Works and Basic Infrastructure has coordinated preparations with railway agencies and engineering consultancies. The programme aims to extend links between southern provinces and transport infrastructure further north.
Better rail access could support passenger travel and freight movement across sparsely populated areas. The wider programme also seeks to connect inland economic centres with national markets, while supporting future regional trade.
Tender details remain the next milestone
The tender remains open, with bids due on 10 November 2026. ANESRIF, the National Agency for Studies and Monitoring of Railway Investment Projects, is the tendering authority. The contract value and successful contractor have not yet been announced.
The stated qualification thresholds call for substantial experience in railway work and bridge construction, as well as track maintenance. Bidders must also have specialised equipment and high construction turnover. Eligible individual firms and consortia may participate.
The tender is underway, and the presidential directive sets Tamanrasset as the starting point for the wider railway project. The next procurement milestone is the submission of bids.