• 2 mins read
  • Published
  • Updated

Nouakchott West Substation Restored to Full Capacity, SOMELEC Confirms

Amal Obeidi Editor Maghreb Insider

Post by Amal Obeidi

Nouakchott West Substation Restored to Full Capacity, SOMELEC Confirms Maghreb Insider © maghrebinsider.com
Nouakchott West Substation Restored to Full Capacity, SOMELEC Confirms © maghrebinsider.com

SOMELEC's director general announced that Nouakchott's west substation is now operating at full capacity, restoring electricity to affected districts. Repairs at the east substation are ongoing, with half its capacity already back online.

SOMELEC Director General Akhrambali Lehbib has confirmed that the west substation in Nouakchott is operating at full capacity after recent disruptions left several districts without electricity. All lines supplying the previously affected neighbourhoods have been re-energised, Lehbib told the Mauritanian News Agency.

Lehbib said the west substation is equipped with three lines, allowing it to draw power from both the Dial and Arafat power plants. The substation is now operating far more reliably than it did during the outage.

East Substation Repairs Progressing

At the east substation, SOMELEC teams restored approximately 50% of its capacity two days ago, Lehbib said. Repairs to the remaining half are nearing completion, after technical teams worked continuously for three days to address the faults. Lehbib said the effort was warranted given the importance of reliable service for citizens.

Measures to Prevent Future Outages

Lehbib said SOMELEC is pursuing a two-part approach: implementing immediate solutions to secure electricity supply for residents and critical sectors, while reviewing and strengthening measures to protect substations from similar incidents. This includes reassessing and upgrading protocols for substation security and ability to recover.

The restoration work follows a period of impressive disruption. A major fire at the eastern substation caused widespread outages and prompted urgent repairs and the rerouting of electricity across Nouakchott. For further background on the initial incident and emergency response, see this earlier coverage.

Related Briefs