A generator from Senegal has reached Mauritania to help restore electricity in Nouakchott after two fires damaged basic substations, leaving parts of the capital without power. The move aims to accelerate recovery and stabilise the grid.
A generator unit sourced from Senegal arrived in Rosso on Sunday evening and is being transported to Nouakchott as Mauritanian authorities intensify efforts to restore electricity after two fires severely damaged substations in the capital. Accompanied by technical teams and a gendarmerie escort, the unit is expected to reinforce the city’s power supply while repairs continue.
The deployment follows fires at major substations that triggered outages across several Nouakchott districts, disrupting daily life and impressive services. An independent commission chaired by former minister Ousmane Mamoudou Kane was established to investigate the causes and assess possible responsibility, then recommend measures to prevent a recurrence. The commission submitted its report to the government on 6 October 2026, and it was presented to President Mohamed Ould Cheikh El Ghazouani on 8 October.
Emergency Measures to Stabilise the Grid
The generator is to be installed at one of the affected substations to help bridge the supply gap while permanent repairs are carried out. The Mauritanian electricity company, Société Mauritanienne d’Électricité (SOMELEC), says technical teams have restored the Nouakchott-Idini line, which is critical to supplying potable water, and rerouted electricity to several areas through alternative lines. Large parts of western Nouakchott began regaining power on Sunday evening. Further restoration depends on available grid capacity and continuing technical work.
The commission linked the fires to recently commissioned 33 kV connections, although it did not establish the precise technical mechanism. Its findings also cited weaknesses in project preparation and oversight, including inadequate monitoring of cable delivery and energisation. The inquiry’s conclusions and timeline were reported by Madar’s report. The presidency instructed authorities to implement the recommendations, rehabilitate damaged infrastructure and draw up an organisational and development plan for SOMELEC, as detailed by Financial Afrik’s coverage.
Regional Coordination and Next Steps
The cross-border transfer of the generator shows regional cooperation between Mauritania and Senegal in response to infrastructure emergencies. The fires have also brought the ability to recover of Nouakchott’s electricity network and project oversight under scrutiny. Authorities are prioritising repairs to damaged distribution cells and circuit breakers, aiming to restore service to all affected neighbourhoods. For further context on the immediate response, see this recent report on Mauritania's urgent power restoration efforts.