ONEE said severe weather damaged four 225 kV lines serving substations around Casablanca and Nouaceur. The outage disrupted urban services as unsupported cyberattack claims circulated online.
A widespread electricity outage began in Casablanca at 4:55 p.m. on Wednesday, November 11, during Storm Charles. Power began returning at 6:23 p.m., ONEE said, and all affected source substations were fully resupplied by 8:54 p.m., nearly four hours after the interruption began. The utility called the event exceptionally rare and attributed it to simultaneous damage to four 225 kV transmission lines supplying the Ouled Haddou and Dar Bouazza substations.
The outage affected the city center, Maârif, El Fida, Aïn Chock, Ben M'sick, Sbata, Sidi Othmane, Hay Hassani and parts of Nouaceur province. Local media reported that traffic lights stopped working and tram service halted on some sections. Internet and telecommunications outages were also reported in affected areas. Storm-related disruption extended to airport, port and road operations.
Storm damage hit primary and backup feeds
ONEE, Morocco's National Office of Electricity and Drinking Water, said strong winds and thunderstorms along the country's northern Atlantic coast damaged the four transmission lines. The circuits carried both the main and alternative electricity feeds to the two substations, cutting primary and backup supply routes at the same time. ONEE activated a crisis-management unit and sent technical teams to restore service.
The outage unfolded amid severe weather across Morocco. Casablanca airport recorded a wind gust of 107.4 km/h, the strongest reported in the country that day. Storm Charles also brought heavy rain and localized flooding, with rainfall exceeding 100 millimeters in parts of the Agadir Ida-Outanane region. In Casablanca, reports of wider storm impacts included a death and a serious injury.
In a statement issued Thursday, November 12, ONEE said crews worked in adverse weather, apologized for the disruption and would maintain enhanced monitoring while conditions persisted. Le360 reported the utility's timeline and explanation.
Cyberattack claims remain unsupported
Speculation about a cyberattack spread on social media after the outage. Online claims also linked it to a predicted global blackout on November 17, 2026. ONEE attributed the Casablanca failure to storm damage to the transmission lines; reports on the incident identified no evidence of cyber intrusion and made no connection between the outage and a global event.
The regional energy-security angle differs from an earlier report on Algeria's Niger deployment, which concerned a troop mission. ONEE attributed the Casablanca disruption to the storm.